S/4HANA Transformation for Smart Manufacturing
Fortune 500 Manufacturer
Business Context
The organization and its strategic environment
A $12B Fortune 500 manufacturer with 28 plants across North America faced SAP ECC end-of-support deadlines. The company's production planning relied on spreadsheets, supply chain visibility was limited to 48-hour windows, and inventory carrying costs were $180M annually.
Technology Landscape
Systems and infrastructure before DGT
SAP ECC 6.0 with 1,400+ custom ABAP programs, 6 bolt-on MES systems, Oracle data warehouse, manual production scheduling in Excel, and limited EDI connectivity with 200+ suppliers.
The Challenge
What the client was facing
Heavily customized SAP ECC 6.0 facing end-of-support, spreadsheet-based production planning causing 12% schedule adherence gaps, 48-hour supply chain visibility windows, and $180M in excess inventory carrying costs.
The DGT Solution
How DGT addressed the challenge
DGT executed a greenfield S/4HANA implementation with embedded analytics, integrated MES connectivity, real-time supply chain visibility, and AI-powered demand sensing. DataBridge migrated 14 legacy systems with 99.8% accuracy.
DGT Accelerators Used
Delivery Approach
How DGT executed the engagement
Big-bang go-live approach with 6-month parallel run. DGT deployed a 22-person team across functional and technical workstreams. Weekly cutover rehearsals for the final 8 weeks ensured zero-downtime go-live.
Governance Model
How the engagement was managed
C-suite steering committee (monthly), program director with DGT and client co-leads, 6 functional workstream owners, weekly risk register review, and dedicated cutover command center.
Timeline & Phases
The execution roadmap
Discovery & Blueprinting
6 weeksFit-gap analysis, custom code remediation plan, data migration strategy
Core Build
12 weeksS/4HANA configuration, MES integration, supplier portal
Data Migration
4 weeksDataBridge migration of 14 systems, 3 mock cutovers
Testing & Validation
6 weeksIntegration testing, performance testing, UAT across 28 plants
Go-Live & Hypercare
6 weeksBig-bang cutover, 24/7 war room, stabilization
Risks Addressed
Key risks DGT mitigated during the engagement
Why DGT Won
What set DGT apart in this engagement
Outcome Metrics
Measurable before-and-after results
| Metric | Before | After DGT |
|---|---|---|
| Schedule Adherence | 78% | 94% |
| Inventory Carrying Cost | $180M/yr | $126M/yr |
| Supply Chain Visibility | 48 hours | Real-time |
| Custom ABAP Programs | 1,400+ | 180 (87% retired) |
The Impact
Headline results delivered
"DGT's DataBridge accelerator made our S/4HANA migration seamless. We went live on schedule with zero data quality issues."
David Park
CIO, Fortune 500 Manufacturer